Tuesday 27 March 2012

Water discharge pipe

During May 2012, Transcity will install a small 150mm pipe to provide an outlet for water from the tunnels during construction. This pipe will connect into the existing stormwater drain in Dean Street, Toowong. It is expected that this activity will take approximately two to three weeks to complete.

Transcity has developed a route for the pipe that will run alongside and between the existing bike and pedestrian paths, ensuring that the work is undertaken within previously disturbed areas of ANZAC Park.

Transcity is liaising with the Friends of ANZAC Park and heritage experts to ensure any areas of heritage significance are avoided during this work.

The work will involve the installation of a pipe under the Western Freeway via an underbore from the area within the shared user path ramp to the western worksite. This will then connect into a newly laid section of pipe that will be installed via into a small trench adjacent to the bike path, which leads to the stormwater drain in Dean Street. Transcity will reinstate and returf all work areas once complete.

In coming days, Transcity will complete a visual survey of the area. Once the design is confirmed, Transcity will be able to provide further details on this work to keep the community and park users informed.

For more information, please contact Stephen or Melissa from Transcity on 1800 778 772.

Wednesday 14 March 2012

Invitation from the Ada Parkers to the ANZAC Parkers

"Well done MCRG on the $50,000 pledge for your much-loved Ada Park from Andrew Fraser MP." Friends of Anzac Park Toowong (FAPT)
"Thanks FAPT!! The Mountainfolk cordially invite their friends the Anzac Parkers to the BBQ. Hope to see our friends from over the overpass there!" Mt Coot-tha Residents' Group (MCRG)

Tuesday 13 March 2012

Latest Legacy Way Project Update

For the latest Legacy Way project update, outlining upcoming activities on the western end of the project please visit

Note: Controlled blasting along the Western Freeway
http://www.transcityjv.com.au/march-2012-construction-update-western-worksite-toowong

Please contact the Transcity Community Relations team on 1800 778 772 or at info@transcityjv.com.au for more information.

Sausage Tree in bloom, ANZAC Park. Photo by Mim

Thursday 1 March 2012

Access road construction begins/ Westside News article 29 February 2012

Work has begun on the access road on BCC land adjoining ANZAC Park below the Dog Off-Leash Area for the water main relocation works. If you have any questions please contact the Transcity Community Relations Team:

Phone: 1800 778 772
Email: info@transcityjv.com.au
Visit: Legacy Way Visitors’ Centre
Level 2, 80 Jephson Street, Toowong



Westside News 29 February 2012
Dog off-leash park will remain open during tunnel construction works

A DECISION on the location of a temporary road in Toowong has Friends of Anzac Park sighing with relief.
Transcity has revealed that work will start this month on a road running alongside Anzac Park – instead of through it – to relocate a water main for construction of the Legacy Way Tunnel’s entry and exit lanes.
Trancity’s letter to local residents said: ‘‘A temporary light-vehicle access track will run from the work area to the end of Broseley Rd. The dog off-leash area will not be impacted by these works and access to the Broseley Rd footpath and bikeway will be maintained.’’
Geoff Murray from the Friends of Anzac Park said:
‘‘Transcity are conducting themselves in a way in which they are respecting the sensitivity of the park’’.
Water mains work should be finished in June.